ADKO Engineering was selected to provide Construction Management for the construction of new five bridges for Sperry Road Extension Project. These new five bridges consist of 3 span cast-in-place P/S box girder on seat type abutments and 648-14” square Precast P/S Concrete Piles. Coordination included multiple projects in the vicinity of the project. This includes PG&E’s raising of power lines and Delta Water. Consultant’s responsibilities: Provided Structures Representative on site. Coordination with other agencies, on-going consultation and interpretation of construction documents during the construction of the proposed project, attended the project pre-construction meeting; reviewed and commented on contract change orders; prepared plan revisions as necessitated by contract change orders; provided construction engineering assistance as required; reviewed and approved all submittals and shop drawings.
Construction Value: $60 Million
ADKO Fee: $1,500,000
Client Reference: Omar Al Hindi